Page 37 - Analysis Report of Global Market in the Submarine Cable Field (2017)
P. 37

Hengtong Marine System Integration Area with subsea plant & cable bights  The 500m HOUC & HORC plough burial trials were located in the area
                                                                 28°33’N   130°43’E
                                                                 Four separate sea trial systems were manufactured specifically for the sea
                                                                 trials
                                                                 ●  500m water depth HORC-1 cable plough trial (2fp & 6fp RPTs, 2 x
                                                                 UJs) using 10.350 kms SAL, SA and DA cables




          When load out operations commenced on 11 April 2017, the Hengtong
          HV company were also loading out products, so the gantry system &
          Port successfully demonstrated triple line load outs, showing no conflict
          been the two cable factories onsite.
          Hengtong Marine Port & Gantry, with triple line loading in progress (2 x
          Telecom, 1 x HV)





                                                                 ● 4000m water depth HORC-1 Branching Unit system (PSBU, 5 x UJs)
                                                                 using 25.640 kms re-used LW & LWP cables from the 5000m trial






          The marine portion of the sea trial operation covered 30 days of activity
          over the timeline from 2017.4.11 to 2017.5.10

          Hengtong Marine HOUC-1 un-repeatered cable and HORC-1 repeatered
          cable products were integrated with HMN R1(2 fiber pair) repeaters &
          R2 (6 fiber pair) repeaters and Universal Joints & Universal Quick Joints.
          Integration of BU, R1  Repeater, R2 Repeater and cable joints into the sea
          trail cable systems
                                                                 ●  500m water depth HORC-1 cable plough trial (2fp & 6fp RPTs, 2 x
                                                                 UJs) using 10.350 kms SAL, SA and DA cables
                                                                  MD3 Plough recovery and Plough Graphic Control Screen showing cable
                                                                  burial




          SBSS was selected as the preferred marine operator and the CS Fu Hai
          was mobilized to Hengtong Port for the project, equipped with a SMD
          MD3 cable burial plough capable of 2m to 3m burial into the seabed.
          Three sea trial locations were selected for the trials, generally lying to
          the South and South East of Japan, in an open exposed Pacific Ocean   ● 500m water depth HOUC-1 un-repeatered cable plough burial trial (3
          location.
                                                                  x UQJs) using 6.890 kms SAL, SA and DA cables













          The 5000m HORC Repeatered system trial was located in the area
          28°01’N   134°58’E
          The 4000m HORC branching unit system trial was located at 28°15’N
          133°12’E